MRCA Plans Opening Seven New Gates Between PCH And The Ocean

By Hans Laetz · Fri Dec 13 2019

MRCA Plans Opening Seven New Gates Between PCH And The Ocean
The MRCA has filed plans to reconstruct 10 existing beach accessways, and build seven new ones, in Malibu.
The proposal is structured to bypass the City of Malibu and will be sent instead to the California Coastal Commission for permits.
But the city says the plan must come through the city council for a Coastal Development Permit. About 10 years ago, the MRCA tried a similar end run around the city but lost in court.
"If the project is within the city they have CEQA obligations to consult with the city and it will likely need a CDP," said assistant city attorney, Trevor Rusin, in an interview Thursday.
The MRCA is the Mountains Recreation and Conservation Authority, the same body appointed by two parks districts in Simi Valley and Thousand Oaks. MRCA's co-sponsor is the Santa Monica Mountains Conservancy, another appointed body.
Neither agency has any voting representation from Malibu.
According to the report, the new beach accessways would be built primarily on private land where the owner was forced to dedicate a "vertical easement"between PCH and the water in order to get a Coastal Development Permit.
The seven new accessways would be at:
Buried deep in the report, the MRCA discloses that the proposed public accessways "are not anticipated to be built all at once, but rather as funding becomes available."
But, nevertheless, the CEQA (California Environmental Quality Act) study predicts that "the project could have a potential significant impact on the environment," such as causing additional PCH traffic and parking pressures, the MRCA said in a document released Thursday.
Under CEQA, the agency has to prepare an initial evaluation of the project. MRCA's initial statement found that the new gates could:
The CEQA study also found that the planned beach accessways might have a substantial adverse effect on riparian habitat in state or federally protected wetlands and might interfere substantially with the movement of native resident or migratory fish or wildlife species.
One gate might require construction that would endanger a tree that is protected under the city's native tree ordinance.
As written, the plan's lead agency would be the MRCA and Coastal Conservancy, with approval only by the Coastal Commission.
No mention of consulting with the city, or seeking Coastal Development Permits, is mentioned in the 120-page Initial Statement from the MRCA.
State courts have ruled that the legal vehicle used by the MRCA to get around the city, called a CEQA Public Works Project, cannot be used to bypass a city that has a Local Coastal Program certified by the Coastal Commission, such as Malibu.
A version of this story appeared onĀ KBUU News.

View on The Malibu Times