To help plan around the road work, the schedule for the upcoming maintenance is as follows:
- October 21-22: Latigo Canyon Road—Asphalt Rubber Overlay
- October 23-24: Corral Canyon Road—Asphalt Rubber Overlay
- October 24-25: Philip Avenue—Slurry Seal
- October 24-25: Cuthbert Road—Slurry Seal
- October 24-45: Calpine Drive: Slurry Seal
- October 25-31: Striping/ Pavement Markings