City Street Maintenance Expected to Cause Delays

0
369
City Logo

The City’s Public Works Department will be working on several city streets in coming weeks as part of their ongoing Street Maintenance Project. 

Crews will be working on roads Monday through Friday from 7 a.m to 4 p.m. until October 31, according to the city. Lanes will be closed with traffic control implemented during these hours.

Delays are to be expected and residents are advised to allow extra time for their commutes to and from work.

To help plan around the road work, the schedule for the upcoming maintenance is as follows:

  • October 21-22: Latigo Canyon Road—Asphalt Rubber Overlay
  • October 23-24: Corral Canyon Road—Asphalt Rubber Overlay
  • October 24-25: Philip Avenue—Slurry Seal
  • October 24-25: Cuthbert Road—Slurry Seal
  • October 24-45: Calpine Drive: Slurry Seal
  • October 25-31: Striping/ Pavement Markings